How we size ESS for peak shaving with 15 minute data
Korean industrial tariffs bill the highest 15 minute demand for a year. Our method: a full year of KEPCO data, two dispatch models and a capacity sweep.
Why 15 minute data
In Korea the monthly basic charge of an industrial customer is set by the single highest 15 minute demand, and that peak can follow the customer for a year. An ESS sized for peak shaving therefore has to be sized from the full year of 15 minute readings, not from monthly bills.
Most of our ESS work is for factories on the KEPCO industrial (B) tariff. The tariff is simple to read and easy to misjudge, so we built our own analysis engine around the 15 minute meter data that KEPCO lets every customer download. This article walks through the method and one published case.
The tariff in four facts
| Item | Industrial (B), high voltage A, option II (2026) |
|---|---|
| Basic charge | 8,320 KRW per kW of billing demand per month |
| Billing demand | The highest of this month's 15 minute peak, the highest peak of December, January, February, July, August and September in the previous 12 months, and 30% of contract demand |
| Energy charge | Off peak 116.0 to 123.0, mid peak 133.4 to 164.0, on peak 150.9 to 229.0 KRW/kWh by season |
| Time bands | Off peak 22:00 to 08:00. On peak 15:00 to 21:00 in summer, spring and autumn, 09:00 to 12:00 and 16:00 to 19:00 in winter. Saturday on peak is billed as mid peak, Sundays and holidays as off peak |
The ratchet in the second row is the reason a short peak is expensive. One bad quarter hour in January sets the billing demand for the following twelve months. Climate and environment charges (9.0 KRW/kWh), the fuel cost adjustment (5.0 KRW/kWh) and the 2.7% power fund are added on top, and our engine applies all of them.
Step 1: read and clean a full year
We import the KEPCO PowerPlanner export directly. A clean year has 96 intervals per day, so the first check is simple: the interval count must equal the number of days times 96. Duplicated days and gaps are repaired and the repairs are listed in the report, because a missing winter morning can hide the very peak we are trying to cut. Billing months follow the customer's meter reading day, not the calendar month.

Step 2: two ways to run the battery
We simulate every candidate system twice. The first run is a linear program (solved with HiGHS) that knows the whole year in advance. It gives the theoretical maximum saving, the same kind of number that HOMER or REopt report. The second run is a rule based controller that behaves like a real EMS: it only sees the past 14 days, sets a peak target from them with a 20 kW margin, charges at night, absorbs surplus solar and never exports. The gap between the two runs is the price of not knowing the future. We base the investment decision on the second, realistic run.
To make sure the engine agrees with the tools banks know, we ran a plant through HOMER Grid 1.11.7 with identical assumptions. The bills with no system and with solar only matched within 0.01%, the bill with solar plus ESS within 1%, and the ESS saving differed by 2.01%, as expected, because our optimal run sees the full year.
Step 3: sweep the capacity
We never size a battery from a rule of thumb. The engine runs the same year for a range of capacities, typically 250 to 2,000 kWh, and computes the saving, the 20 year cash flow, NPV, IRR and payback for each. The result is a curve, and the best size is where NPV peaks, not where savings peak.
A published case
One factory we analysed, a manufacturer with a billing demand of about 650 kW, shows why. Its demand exceeded 600 kW for only 19 hours in a whole year, and those peaks came in the morning, before rooftop solar produces much. Solar alone left the morning peak untouched, and on weekends the plant was idle and solar power was surplus.
| Result | Value |
|---|---|
| Capacity sweep | 250 to 2,000 kWh; best band 500 to 750 kWh; 3,000 kWh not paid back within 20 years |
| Selected battery | About 630 kWh from actual product combinations |
| Billing demand after PV and ESS | About 400 kW on clear days, about 510 kW on the worst day without solar |
| Electricity bill index | Today 100, solar only 68, solar plus ESS 58 |
| Simple payback | Solar only 5.7 years, solar plus ESS 6.4 years, ESS alone 8.8 years |
We valued the saving at the worst day, about 510 kW, because billing demand is set by the worst quarter hour of the year, not by an average sunny day. Even on that basis, adding the battery gave about 17% more 20 year net present value than solar alone. The calculation used a 20 year period, a 4.5% discount rate and no tariff increase; any tariff increase shortens the payback.
The same method gives a different answer elsewhere. A plant that peaks at noon or runs seven days a week gets far more from solar and less from storage, and long cable routes on site can add more than a year to the ESS payback. That is why we run the sweep for every site.
What the client receives
- A decision report with a clear verdict (recommended, conditional or not recommended) based on the realistic payback.
- A revenue workbook with live formulas, so the owner can change unit costs and rates and see payback and IRR update.
- A one page grid monitor view showing a typical weekday and holiday, charge and discharge times and state of charge.
- A number check: every figure in the report is compared with the engine output before the PDF is issued.
Before you ask for a quote
Download the last 12 months of 15 minute data from KEPCO PowerPlanner and send it with one recent bill. With those two files we can tell you within days whether peak shaving pays on your site, and how large the battery should be.
If you are planning a project in Korea and want this check done on your site, email the drawings or the parcel list to info@ecokkorea.co.kr. We reply with the scope and schedule first.
Sources: KEPCO 2026 tariff for industrial (B) high voltage A option II as applied in PowerPlanner; Electricity Business Act Enforcement Decree Article 36 for the power fund; our analysis engine documentation and validation log; our published Korean case studies on the same factory (no client name).
More insights
- Korean solar permitting setback rules explained
- PVsyst vs Solar Pro cross-check on a 619 kWp roof
- Agrivoltaic structure design basics
- Electrical BOQ and quantity take-off workflow
- Korea industrial electricity tariff 2026: rates, demand charges and a worked bill
- Solar permitting in Korea: the seven steps, statutory periods and a real timeline
- Net metering in Korea: the Article 18 rules and what changes on the bill
- Korea's agrivoltaics act: who can build, where, for how long, and the draft design rules
- Peak shaving ESS payback in Korea: a worked example with 2026 tariffs
- P50 and P90 for solar in Korea: how we build a bankable yield estimate
- BESS feasibility study in Korea: what a bankable analysis contains and how we cross check it
- Rooftop solar structural review in Korea: loads, anchors, reinforcement and the permits that follow
- Fire alarm and telecom design and BOQ in Korea: separate contracts, detector counts and the quantities that get missed
- Solar project timeline in Korea: how long each stage really takes, from license to commercial operation