Korea industrial electricity tariff 2026: rates, demand charges and a worked bill
KEPCO industrial rates by class, voltage, option, season and time band in KRW, the billing demand rule, and a full winter bill of 27,347,780 KRW worked line by line.
The short answer
As of November 2026, a Korean factory pays between 88.0 and 242.9 KRW per kWh for energy, depending on its tariff class, the season and the time of day, plus a monthly demand charge of 5,550 to 9,810 KRW per kW. On top of those come a climate charge of 9.0 KRW/kWh, a fuel cost adjustment of 5.0 KRW/kWh, 10% VAT and a 2.7% power industry fund.
Foreign owners and EPC contractors usually meet the Korean industrial tariff through a KEPCO bill they cannot read, or through a feasibility model that uses one flat rate. Both hide the two things that drive a factory bill here: a demand charge that is set by a single 15 minute peak, and energy rates that differ by almost two to one between night and afternoon. This article lays out the 2026 tariff in one place, in KRW, with a worked bill.
All rates below are taken from the KEPCO tariff table in force since 1 June 2026 (the industrial (B) class since 16 April 2026) and are quoted before VAT and the fund.
How the industrial tariff is organised
KEPCO splits industrial customers by contract demand. Industrial (A), written 산업용(갑) on the bill, covers contract demand under 300 kW. Industrial (B), 산업용(을), covers 300 kW and above and is always billed by time of day. Within each class the supply voltage sets the row: low voltage at 220 or 380 V, high voltage A from 3.3 kV to 66 kV (the 22.9 kV service that most factories take), high voltage B at 154 kV and high voltage C at 345 kV.
High voltage customers then choose an option, numbered I, II and III. Each step up raises the monthly demand charge and lowers the energy rate, so the right option depends on how many hours a month the plant runs at its billing demand. KEPCO's own tariff table describes option I as suited to customers with few hours of use, option II to customers with many, and option III to customers using more than 500 hours a month, where hours of use means monthly kWh divided by billing demand.
Industrial (A) I: under 300 kW, one rate per season
| Contract demand under 300 kW | Demand charge (KRW/kW/month) | Summer (Jun to Aug) | Spring and autumn (Mar to May, Sep to Oct) | Winter (Nov to Feb) |
|---|---|---|---|---|
| Low voltage | 5,550 | 116.2 | 94.4 | 114.5 |
| High voltage A, option I | 6,490 | 124.8 | 101.1 | 124.7 |
| High voltage A, option II | 7,470 | 120.0 | 96.5 | 118.2 |
| High voltage B, option I | 6,000 | 123.6 | 100.0 | 123.2 |
| High voltage B, option II | 6,900 | 118.9 | 95.4 | 117.1 |
A small workshop on low voltage therefore pays 116.2 KRW/kWh in summer, 94.4 in spring and autumn and 114.5 in winter, plus 5,550 KRW for every kW of contract demand each month whether or not it is used.
Industrial (A) II: under 300 kW with a time of use meter
| Time of use meter | Demand charge | Off peak (summer, spring/autumn, winter) | Mid peak | On peak |
|---|---|---|---|---|
| High voltage A, option I | 6,490 | 95.7, 95.7, 103.1 | 121.5, 100.5, 120.0 | 155.0, 119.7, 149.4 |
| High voltage A, option II | 7,470 | 90.8, 90.8, 98.2 | 116.6, 95.6, 115.1 | 150.1, 114.8, 144.5 |
| High voltage B, option I | 6,000 | 92.5, 92.5, 99.7 | 120.1, 99.1, 117.7 | 153.9, 117.9, 146.4 |
| High voltage B, option II | 6,900 | 88.0, 88.0, 95.2 | 115.6, 94.6, 113.2 | 149.4, 113.4, 141.9 |
Industrial (B): 300 kW and above, always by time of day
| High voltage A | Demand charge (KRW/kW/month) | Time band | Summer | Spring and autumn | Winter |
|---|---|---|---|---|---|
| Option I | 7,220 | Off peak / mid peak / on peak | 121.5 / 169.3 / 234.5 | 121.5 / 138.9 / 156.4 | 128.5 / 169.5 / 210.1 |
| Option II | 8,320 | Off peak / mid peak / on peak | 116.0 / 163.8 / 229.0 | 116.0 / 133.4 / 150.9 | 123.0 / 164.0 / 204.6 |
| Option III | 9,810 | Off peak / mid peak / on peak | 115.1 / 163.2 / 216.6 | 115.1 / 132.1 / 142.6 | 122.4 / 163.4 / 193.4 |
High voltage B customers at 154 kV pay demand charges of 6,630, 7,380 and 8,190 KRW/kW for options I, II and III, and high voltage C at 345 kV pays 6,590, 7,520 and 8,090. Their energy rates sit slightly above the high voltage A rows; the highest single rate in the table, 242.9 KRW/kWh, is the summer on peak rate for high voltage B option I. Industrial (B) customers also get a 50% discount on energy used between 11:00 and 14:00 on Saturdays, Sundays and public holidays in spring and autumn.
The time bands
- Off peak: 22:00 to 08:00 in every season.
- On peak: 15:00 to 21:00 in summer, spring and autumn; 09:00 to 12:00 and 16:00 to 19:00 in winter.
- Mid peak: every other hour.
- On Saturdays, on peak energy is billed at the mid peak rate. On Sundays and public holidays, both energy and maximum demand are recorded as off peak.
The demand charge is not applied to contract demand but to billing demand: the largest 15 minute maximum demand among December, January, February, July, August and September of the previous twelve months and the current month, with a floor of 30% of contract demand. One high quarter hour in January therefore sets the demand charge until the following January. We explain the rule and the ways to lower it in our note on lowering a factory demand charge.
A worked bill: industrial (B), option II, one winter month
Take a factory on high voltage A, option II, with a billing demand of 400 kW and a monthly use of 120,000 kWh split into 40,000 kWh off peak, 50,000 kWh mid peak and 30,000 kWh on peak.
| Line | Calculation | KRW |
|---|---|---|
| Demand charge | 400 kW × 8,320 | 3,328,000 |
| Energy charge | 40,000 × 123.0 + 50,000 × 164.0 + 30,000 × 204.6 | 19,258,000 |
| Climate and environment charge | 120,000 × 9.0 | 1,080,000 |
| Fuel cost adjustment | 120,000 × 5.0 | 600,000 |
| Electricity charge before tax | 24,266,000 | |
| VAT 10% | 2,426,600 | |
| Power industry fund 2.7% | Rounded down to 10 KRW | 655,180 |
| Amount billed | 27,347,780 |
That is 202.2 KRW/kWh on the electricity charge and 227.9 KRW/kWh on the amount billed. If the plant could move its 30,000 on peak kWh into the off peak band, the energy line would fall by 30,000 × (204.6 − 123.0) = 2,448,000 KRW in that month alone, which is why load shifting and storage are the first things we look at for Korean factories.

What foreign models usually get wrong
- Using one blended rate. A Korean factory running a day shift pays a very different average from a plant running three shifts, because of the on peak and off peak split.
- Treating the demand charge as a function of contract demand. It is set by billing demand, and billing demand is set by the worst 15 minutes of the summer and winter months.
- Forgetting the add ons. Climate charge, fuel cost adjustment, VAT and the 2.7% fund together add roughly 25% to the headline energy rate in the example above.
- Converting to dollars too early. KEPCO revises the energy and demand rates by notice, and the fuel cost adjustment changes every quarter (+5.0 KRW/kWh for October to December 2026), so a model should carry KRW rates with a date on them.
What we provide
For a factory in Korea we read the actual bills, identify the class, voltage and option on them, and rebuild twelve months of charges from KEPCO's 15 minute data. From that we check whether a different option would cost less, and whether solar, storage or operating changes would lower the billing demand. The first diagnosis from bills and interval data is free.
If you are planning a project in Korea and want this check done on your site, email the drawings or the parcel list to info@ecokkorea.co.kr. We reply with the scope and schedule first.
Sources: KEPCO electricity tariff table (comprehensive) in force 1 June 2026, industrial (B) and EV charging rates in force 16 April 2026; climate and environment charge 9.0 KRW/kWh under the addendum to the operating guideline of Annex 7 of the Basic Supply Terms; fuel cost adjustment +5.0 KRW/kWh for October to December 2026 per KEPCO notice; VAT 10% and power industry fund 2.7% (fund rounded down to 10 KRW). Rates change when KEPCO revises them, so confirm against the current bill and KEPCO ON before signing anything.
More insights
- Korean solar permitting setback rules explained
- How we size ESS for peak shaving with 15 minute data
- PVsyst vs Solar Pro cross-check on a 619 kWp roof
- Agrivoltaic structure design basics
- Electrical BOQ and quantity take-off workflow
- Solar permitting in Korea: the seven steps, statutory periods and a real timeline
- Net metering in Korea: the Article 18 rules and what changes on the bill
- Korea's agrivoltaics act: who can build, where, for how long, and the draft design rules
- Peak shaving ESS payback in Korea: a worked example with 2026 tariffs
- P50 and P90 for solar in Korea: how we build a bankable yield estimate
- BESS feasibility study in Korea: what a bankable analysis contains and how we cross check it
- Rooftop solar structural review in Korea: loads, anchors, reinforcement and the permits that follow
- Fire alarm and telecom design and BOQ in Korea: separate contracts, detector counts and the quantities that get missed
- Solar project timeline in Korea: how long each stage really takes, from license to commercial operation
