Korea industrial electricity tariff 2026: rates, demand charges and a worked bill

KEPCO industrial rates by class, voltage, option, season and time band in KRW, the billing demand rule, and a full winter bill of 27,347,780 KRW worked line by line.

Tariffs · ECO K KOREA engineering team · 2026-11-12

The short answer

As of November 2026, a Korean factory pays between 88.0 and 242.9 KRW per kWh for energy, depending on its tariff class, the season and the time of day, plus a monthly demand charge of 5,550 to 9,810 KRW per kW. On top of those come a climate charge of 9.0 KRW/kWh, a fuel cost adjustment of 5.0 KRW/kWh, 10% VAT and a 2.7% power industry fund.

Foreign owners and EPC contractors usually meet the Korean industrial tariff through a KEPCO bill they cannot read, or through a feasibility model that uses one flat rate. Both hide the two things that drive a factory bill here: a demand charge that is set by a single 15 minute peak, and energy rates that differ by almost two to one between night and afternoon. This article lays out the 2026 tariff in one place, in KRW, with a worked bill.

All rates below are taken from the KEPCO tariff table in force since 1 June 2026 (the industrial (B) class since 16 April 2026) and are quoted before VAT and the fund.

How the industrial tariff is organised

KEPCO splits industrial customers by contract demand. Industrial (A), written 산업용(갑) on the bill, covers contract demand under 300 kW. Industrial (B), 산업용(을), covers 300 kW and above and is always billed by time of day. Within each class the supply voltage sets the row: low voltage at 220 or 380 V, high voltage A from 3.3 kV to 66 kV (the 22.9 kV service that most factories take), high voltage B at 154 kV and high voltage C at 345 kV.

High voltage customers then choose an option, numbered I, II and III. Each step up raises the monthly demand charge and lowers the energy rate, so the right option depends on how many hours a month the plant runs at its billing demand. KEPCO's own tariff table describes option I as suited to customers with few hours of use, option II to customers with many, and option III to customers using more than 500 hours a month, where hours of use means monthly kWh divided by billing demand.

Industrial (A) I: under 300 kW, one rate per season

Contract demand under 300 kWDemand charge (KRW/kW/month)Summer (Jun to Aug)Spring and autumn (Mar to May, Sep to Oct)Winter (Nov to Feb)
Low voltage5,550116.294.4114.5
High voltage A, option I6,490124.8101.1124.7
High voltage A, option II7,470120.096.5118.2
High voltage B, option I6,000123.6100.0123.2
High voltage B, option II6,900118.995.4117.1

A small workshop on low voltage therefore pays 116.2 KRW/kWh in summer, 94.4 in spring and autumn and 114.5 in winter, plus 5,550 KRW for every kW of contract demand each month whether or not it is used.

Industrial (A) II: under 300 kW with a time of use meter

Time of use meterDemand chargeOff peak (summer, spring/autumn, winter)Mid peakOn peak
High voltage A, option I6,49095.7, 95.7, 103.1121.5, 100.5, 120.0155.0, 119.7, 149.4
High voltage A, option II7,47090.8, 90.8, 98.2116.6, 95.6, 115.1150.1, 114.8, 144.5
High voltage B, option I6,00092.5, 92.5, 99.7120.1, 99.1, 117.7153.9, 117.9, 146.4
High voltage B, option II6,90088.0, 88.0, 95.2115.6, 94.6, 113.2149.4, 113.4, 141.9

Industrial (B): 300 kW and above, always by time of day

High voltage ADemand charge (KRW/kW/month)Time bandSummerSpring and autumnWinter
Option I7,220Off peak / mid peak / on peak121.5 / 169.3 / 234.5121.5 / 138.9 / 156.4128.5 / 169.5 / 210.1
Option II8,320Off peak / mid peak / on peak116.0 / 163.8 / 229.0116.0 / 133.4 / 150.9123.0 / 164.0 / 204.6
Option III9,810Off peak / mid peak / on peak115.1 / 163.2 / 216.6115.1 / 132.1 / 142.6122.4 / 163.4 / 193.4

High voltage B customers at 154 kV pay demand charges of 6,630, 7,380 and 8,190 KRW/kW for options I, II and III, and high voltage C at 345 kV pays 6,590, 7,520 and 8,090. Their energy rates sit slightly above the high voltage A rows; the highest single rate in the table, 242.9 KRW/kWh, is the summer on peak rate for high voltage B option I. Industrial (B) customers also get a 50% discount on energy used between 11:00 and 14:00 on Saturdays, Sundays and public holidays in spring and autumn.

The time bands

  • Off peak: 22:00 to 08:00 in every season.
  • On peak: 15:00 to 21:00 in summer, spring and autumn; 09:00 to 12:00 and 16:00 to 19:00 in winter.
  • Mid peak: every other hour.
  • On Saturdays, on peak energy is billed at the mid peak rate. On Sundays and public holidays, both energy and maximum demand are recorded as off peak.

The demand charge is not applied to contract demand but to billing demand: the largest 15 minute maximum demand among December, January, February, July, August and September of the previous twelve months and the current month, with a floor of 30% of contract demand. One high quarter hour in January therefore sets the demand charge until the following January. We explain the rule and the ways to lower it in our note on lowering a factory demand charge.

A worked bill: industrial (B), option II, one winter month

Take a factory on high voltage A, option II, with a billing demand of 400 kW and a monthly use of 120,000 kWh split into 40,000 kWh off peak, 50,000 kWh mid peak and 30,000 kWh on peak.

LineCalculationKRW
Demand charge400 kW × 8,3203,328,000
Energy charge40,000 × 123.0 + 50,000 × 164.0 + 30,000 × 204.619,258,000
Climate and environment charge120,000 × 9.01,080,000
Fuel cost adjustment120,000 × 5.0600,000
Electricity charge before tax24,266,000
VAT 10%2,426,600
Power industry fund 2.7%Rounded down to 10 KRW655,180
Amount billed27,347,780

That is 202.2 KRW/kWh on the electricity charge and 227.9 KRW/kWh on the amount billed. If the plant could move its 30,000 on peak kWh into the off peak band, the energy line would fall by 30,000 × (204.6 − 123.0) = 2,448,000 KRW in that month alone, which is why load shifting and storage are the first things we look at for Korean factories.

ESS enclosure beside a Korean factory
Factories on the industrial (B) tariff are where demand charge and time of use arbitrage matter most. Storage sizing starts from the tariff above and a year of 15 minute data.

What foreign models usually get wrong

  • Using one blended rate. A Korean factory running a day shift pays a very different average from a plant running three shifts, because of the on peak and off peak split.
  • Treating the demand charge as a function of contract demand. It is set by billing demand, and billing demand is set by the worst 15 minutes of the summer and winter months.
  • Forgetting the add ons. Climate charge, fuel cost adjustment, VAT and the 2.7% fund together add roughly 25% to the headline energy rate in the example above.
  • Converting to dollars too early. KEPCO revises the energy and demand rates by notice, and the fuel cost adjustment changes every quarter (+5.0 KRW/kWh for October to December 2026), so a model should carry KRW rates with a date on them.

What we provide

For a factory in Korea we read the actual bills, identify the class, voltage and option on them, and rebuild twelve months of charges from KEPCO's 15 minute data. From that we check whether a different option would cost less, and whether solar, storage or operating changes would lower the billing demand. The first diagnosis from bills and interval data is free.

If you are planning a project in Korea and want this check done on your site, email the drawings or the parcel list to info@ecokkorea.co.kr. We reply with the scope and schedule first.

Sources: KEPCO electricity tariff table (comprehensive) in force 1 June 2026, industrial (B) and EV charging rates in force 16 April 2026; climate and environment charge 9.0 KRW/kWh under the addendum to the operating guideline of Annex 7 of the Basic Supply Terms; fuel cost adjustment +5.0 KRW/kWh for October to December 2026 per KEPCO notice; VAT 10% and power industry fund 2.7% (fund rounded down to 10 KRW). Rates change when KEPCO revises them, so confirm against the current bill and KEPCO ON before signing anything.