Solar permitting in Korea: the seven steps, statutory periods and a real timeline
License, development permit, KEPCO connection, pre technical review, construction plan notification, pre use inspection and commencement report, with dates from a 1.35 MW roof.
The short answer
A commercial solar plant in Korea goes through seven stages: feasibility, the generation business license (60 day statutory period), the development permit, the KEPCO connection, the pre technical review and construction plan notification (before any work starts), the pre use inspection (applied for at least 7 days before the inspection date) and commercial operation with a business commencement report. Only some of the stages have a statutory period, so the whole process ran about ten months on a 1.35 MW factory roof we handled.
Foreign developers often ask for a single number: how long does permitting take in Korea? There is no single number, because the law fixes a period for some stages and leaves others to the local office or to KEPCO. What the law does fix is the order. Some steps cannot be swapped, and a plan that ignores that order loses months. Below is the sequence as written in the Electric Utility Act (전기사업법) and its enforcement rule, followed by the real dates from a project.
This article is about a plant that sells power. For a self consumption plant the first four stages are the same and the rest switches to the net metering or private use track, which we cover in a separate note on net metering rules.
The seven stages at a glance
| Stage | Who handles it | Statutory period | Key documents |
|---|---|---|---|
| 1. Feasibility | The developer | None | Land use plan, KEPCO grid capacity check |
| 2. Generation business license | Province (or city/county where delegated) up to 3,000 kW; the Ministry of Climate, Energy and Environment above that | 60 days | License application, business plan, transmission diagram |
| 3. Development permit and structure notification | City or county | Varies by office (not fixed) | Layout drawing, structural review |
| 4. KEPCO connection and contract | KEPCO branch (above 1,000 kW the power is sold through the Korea Power Exchange) | None | PPA application, license, interior wiring drawings |
| 5. Pre technical review and construction plan notification | KESCO (Korea Electrical Safety Corporation) for the review; the province for the notification | Before construction starts | Construction plan, technical data, schedule, specifications, supervisor assignment |
| 6. Pre use inspection | KESCO | Apply 7 days before the inspection; certificate within 5 days | Copy of the accepted notification, design documents, safety manager appointment |
| 7. Commercial operation and commencement report | KEPCO, Korea Energy Agency, licensing authority | Commencement report processed in 14 days | Meter sealing, facility confirmation, commencement report |
Four steps that cannot be reordered
- Construction plan notification before construction. Article 61(3) of the Electric Utility Act requires the notification before work starts. If the module, inverter or protection relay changes after the notification, an amendment is filed before the pre use inspection.
- Pre technical review before the notification. A plant connected at extra high voltage, or of 500 kW or more, must attach the KESCO review report to its notification. Only PV under 500 kW connected at low voltage is exempt (Appended Table 8, Note 3 of the enforcement rule).
- Supervisor assignment before construction. Every new PV plant needs construction supervision regardless of capacity; only general use installations of 10 kW or less are exempt. The assignment confirmation can be filed up to the start date.
- Pre use inspection before commercial operation. The application goes in at least 7 days before the desired inspection date, and the meter is sealed and power is sold only after a pass.
What the notification packet looks like
The construction plan notification is a single form (Form 26 of the enforcement rule) with attachments in a fixed order: the construction plan, the schedule, a topographic map at 1:25,000, the technical specification, the supervisor assignment confirmation and the technical data. The construction plan itself lists the module type, rated output, open circuit voltage, short circuit current and module count, the inverter capacity and the protection devices (Appended Table 8, item 2). Two details trip up first time applicants: the start date on the schedule must fall after the notification date, and the pre use inspection application date must be at least 7 days before the inspection date.

Real dates from a 1.35 MW factory roof
These are the recorded dates from a 1,349.12 kWp roof at a manufacturing plant in the Changwon national industrial complex, connected at extra high voltage, for which we did the design, permitting and construction. Because it exceeds 1,000 kW, the power is sold through the Korea Power Exchange rather than directly to KEPCO.
| Date | What happened |
|---|---|
| 17 October to 24 November 2025 | License application to license: 38 days |
| December 2025 | KEPCO distribution line use application, Korea Power Exchange membership |
| 24 December 2025 to 21 April 2026 | KESCO pre technical review including supplements: about four months |
| From April 2026 | Structure notification, construction plan notification and amendment, construction |
| 21 to 23 July 2026 | Pre use inspection, certificate two days later |
| 29 to 31 July 2026 | Grid interconnection test and meter sealing, then commercial operation |
| 1 August 2026 | Business commencement report filed |
The longest stage was not one with a statutory period. The pre technical review and its supplements took about four months. On another factory roof of 558 kW we handled, the review asked for a working space layout, flood protection for outdoor equipment, a grounding terminal box detail and polarity marking on the module output wiring. Putting those four items into the first set of drawings is the single cheapest way to shorten a Korean permitting schedule.
The business commencement report must be filed within 30 days of the first power trade (Article 9 of the Act). The dated story of a comparable project, with the license, the notification and the inspection records, is in our note on solar permitting in Korea.
Where the offices differ
Whether the province has delegated the license and the notification to the city or county differs from province to province, and the offices in Jeollanam-do and Gwangju follow the rules of the integrated special city from 1 July 2026. We confirm the receiving office before the first filing rather than assuming it from a previous project.
How we run it for a foreign client
- Stage 1 as a written feasibility report: land use, setbacks, grid capacity, with the parcel list and drawings in English on request.
- One schedule that places every filing in the legal order, with the statutory periods marked and the unfixed ones estimated from our own records.
- The notification packet prepared from the design data, so the numbers on the license, the drawings and the notification agree.
- The pre technical review items from our past projects built into the first drawing set.
If you are planning a project in Korea and want this check done on your site, email the drawings or the parcel list to info@ecokkorea.co.kr. We reply with the scope and schedule first.
Sources: Electric Utility Act Articles 9 and 61; Enforcement Rule of the Electric Utility Act Articles 31 and 34, Appended Table 8 and Forms 1, 6 and 26 (Korean National Law Information Center, checked October 2026); Korea Power Exchange and Korea Energy Agency guidance; project records held by the company for the Changwon and Cheonan factory roofs. Statutory periods exclude supplement requests and consultation periods; confirm the receiving office before filing.
More insights
- Korean solar permitting setback rules explained
- How we size ESS for peak shaving with 15 minute data
- PVsyst vs Solar Pro cross-check on a 619 kWp roof
- Agrivoltaic structure design basics
- Electrical BOQ and quantity take-off workflow
- Korea industrial electricity tariff 2026: rates, demand charges and a worked bill
- Net metering in Korea: the Article 18 rules and what changes on the bill
- Korea's agrivoltaics act: who can build, where, for how long, and the draft design rules
- Peak shaving ESS payback in Korea: a worked example with 2026 tariffs
- P50 and P90 for solar in Korea: how we build a bankable yield estimate
- BESS feasibility study in Korea: what a bankable analysis contains and how we cross check it
- Rooftop solar structural review in Korea: loads, anchors, reinforcement and the permits that follow
- Fire alarm and telecom design and BOQ in Korea: separate contracts, detector counts and the quantities that get missed
- Solar project timeline in Korea: how long each stage really takes, from license to commercial operation