KOEN

Solar project timeline in Korea: how long each stage really takes, from license to commercial operation

Dated timelines from two factory roofs (1.35 MW through the power exchange in 9.5 months, 558 kW under a KEPCO agreement in 12 months), the statutory day counts, equipment lead times and what runs in parallel.

Permitting · ECO K KOREA engineering team · 2026-11-12

The short answer

On the factory roofs we have taken from license to commercial operation, the whole process took 9.5 months for a 1.35 MW plant selling through the power exchange and 12 months for a 558 kW plant under a KEPCO purchase agreement. Construction itself was two to six months of that. The rest was permits, the safety corporation review and utility paperwork, and only a few of those steps have a statutory clock: 60 days for the license, an inspection request at least 7 days before the inspection, a certificate within 5 days of it, and a commencement report within 30 days of the first power sale.

The seven stages and who handles each are in our note on Korean solar permitting. This note is about time: how long each stage took on two real projects, which stages can run in parallel, what the law fixes, what the suppliers fix, and where the months were lost.

Two tracks, decided by size

Above 1,000 kW the power is sold through the Korea Power Exchange, which adds membership, meter sealing by the exchange and a trading start confirmation. At 1,000 kW and below the owner signs a power purchase agreement with KEPCO, which adds the contract paperwork and a KEPCO protection coordination review before the meter is sealed. The permits before construction are the same on both tracks.

Timeline A: 1,349 kWp roof, Changwon, sold through the power exchange

DateStepElapsed
17 October 2025Generation business license applicationDay 0
24 November 2025License issued38 days
15 December 2025KEPCO line use application and power exchange membership filed on the same dayDay 59
24 December 2025 to 6 February 2026KESCO pre technical review including seven supplementsAbout 6 weeks
7 January to 6 February 2026Structure notification to the city, four supplements, accepted30 days
26 February 2026Construction plan notification certificateDay 132
7 February to 23 July 2026Construction: safety nets and guardrails, roof overlay, 2,108 modules, trays, substation, 14 inverters; two change notifications for rain and a ready mix concrete strike5.5 months
23 July 2026Pre use inspection passed at the first attempt, certificate two days laterDay 279
29 to 31 July 2026KEPCO interconnection test and meter sealing, power exchange metering seal, trading start, commercial operationDay 287
1 August 2026Business commencement report filed9.5 months from application

Timeline B: 558 kW roof, Cheonan, KEPCO purchase agreement

DateStepElapsed
1 April 2025Generation business license issuedDay 0
April to August 2025Roof survey by drone, three reinforcement options for a 1989 slate roof, buildings changed4 months
28 May to 1 July 2025Structure notification filed and accepted, later cancelled because the buildings changed34 days
29 July to 1 September 2025Major repair permit for added beams and columns, processed with a new structure notification34 days
21 August 2025License amendment from 737.1 kW to 560.16 kW after the building set changedDay 142
26 to 27 August 2025KEPCO impedance data received, purchase agreement documents filedDay 148
5 to 8 September 2025KESCO pre technical review, five supplements closed in three daysDay 160
17 to 25 September 2025Construction plan notification and building commencement report filed the same day; commencement accepted after one supplementDay 177
October 2025 to January 2026Building reinforcement, then modules on six buildings from 11 to 22 December, electrical work in January; change notification on 25 November extended the period to 31 March4 months
11 February 2026Pre use inspection passed (22.9 kV, 558 kW)Day 316
10 to 20 March 2026Purchase agreement signed, interconnection test with the KEPCO monitoring terminal, relay settings entered, meter sealed, commercial operationDay 353
7 April 2026Business commencement report filed12 months from license
Factory roof solar plant in Cheonan, Korea
One of the six buildings at the Cheonan site. The roof survey and the reinforcement of one building set the whole schedule; the electrical construction itself took about two months.

What ran in parallel, and what could not

  • The KEPCO application and, above 1,000 kW, the power exchange membership were filed three weeks after the license, while the structural and KESCO reviews were still open. They do not wait for the construction plan notification.
  • On the PPA track the purchase agreement documents went in before construction started; the agreement itself was signed only after the inspection certificate. Inverter setting confirmations, meter test certificates and other supplier documents for the agreement were requested at the time of ordering.
  • The extra high voltage switchgear and transformer take about 75 days from drawing approval to delivery in our schedules and must be ordered before the construction start date, which the notification itself permits because the notification concerns the work, not the purchase.
  • The structure notification cannot be accepted until the building set is final; in Cheonan it was accepted, cancelled and refiled when the buildings changed, and the license had to be amended for the same reason.
  • The pre use inspection cannot be requested until the notified plan and the built plant match, so every change of module, inverter or protection relay after the notification is filed as an amendment before the inspection request.

The clocks that are fixed

StepPeriodBasis
Generation business license60 days statutory processingElectric Utility Act and its rule
Site manager appointment notice7 days before the start of workElectrical Construction Business Act Enforcement Decree, Article 12-2
Supervisor assignment confirmationBy the construction start dateElectric Utility Act Enforcement Rule, Appended Table 8, note 4
Construction plan notificationBefore work starts; about 15 days to process in practice; amendments before the certificate period expiresElectric Utility Act Article 61(3)
Pre use inspection requestAt least 7 days before the inspection dateEnforcement Rule Article 31(5)
Inspection certificateWithin 5 days of the inspectionEnforcement Rule Article 34(1)
Temporary useUp to 3 months, extendable to one yearEnforcement Rule Article 31-2
KEPCO connection administrationAbout 3 months: 2 months for the connection design and cost notice, 1 month for payment; a 22.9 kV connection of 5 to 10 MW or a new line has a 12 month sample scheduleKEPCO transmission and distribution facility use rules, Article 10
RPS facility confirmationApply within one month of the inspection or certificates start from the application dateKorea Energy Agency guidance
Business commencement reportWithin 30 days of the first power tradeElectric Utility Act Article 9(4)

Durations we plan with

For a first schedule we use a model calibrated on our own projects. The figures are construction days from the first site work to the meter seal, with equipment ordered in advance, and before any weather or review delay.

PlantConstruction daysCritical path
Roof, low voltage, about 100 kW41Rails, modules, string inverter, inspection, seal
Roof, low voltage, about 500 kW45Same, with longer rail and module runs
Carport, low voltage, about 500 kW50Concrete footings and curing, then steel
Roof, extra high voltage, about 1,350 kW98Interconnection switchgear manufacture, about 75 days
Ground, extra high voltage, 1 MW98Switchgear; civil 19, foundations 16, structure 20, modules 20, electrical 18 days
Ground, extra high voltage, 3 MW100Structure 38, modules 40 and stringing 34 days overtake the switchgear

Supplier lead times behind the model: modules about 25 days, roof rails 14, ground structures 18, low voltage string inverters 21, extra high voltage inverters 45, low voltage boards 25, extra high voltage interconnection switchgear 75 and transformers about 75, the last to be confirmed with the maker for each order. July and August civil work is planned 15% longer for the rainy season.

Where the months went

  • Reviews with supplements: seven KESCO supplements and four structure notification supplements in Changwon, five KESCO supplements in Cheonan. Almost all were mismatches between documents (module certificate numbers, relay models, string currents) and are avoidable with one cross check before filing.
  • Weather and strikes: six weeks of rain and a ready mix concrete strike in Changwon moved the completion from 30 June to 31 July and required two change notifications.
  • Roof decisions: four months in Cheonan between the license and a final building set, which then forced a license amendment and a second structure notification.
  • Forms: the building department asked for the structural confirmation on a form with seismic items, and the engineer had to rewrite and seal it.

What to settle before the clock starts

  • The final set of buildings and the capacity, because both appear on the license and on every later form.
  • The structural review and the roof material survey, before the structure notification.
  • The KESCO checklist items that produced supplements on our sites: working space layout, flood protection and fencing of outdoor equipment, switchgear sections, earthing details and string polarity marking.
  • Supplier documents for the KEPCO agreement or exchange registration, requested with the purchase order.

If you send us the parcel or building list and the intended capacity, we return a dated schedule on this template with the parallel tracks drawn in, so that the equipment orders and the filings are placed in the right order from the first week.

If you are planning a project in Korea and want this check done on your site, email the drawings or the parcel list to info@ecokkorea.co.kr. We reply with the scope and schedule first.

Sources: project records of the Changwon (1,349.12 kWp, commercial operation 31 July 2026) and Cheonan (558 kW, commercial operation 20 March 2026) plants we designed, permitted and built; Electric Utility Act Articles 9 and 61 and its Enforcement Rule Articles 31, 31-2 and 34 and Appended Tables 8 and 9; Electrical Construction Business Act Enforcement Decree Article 12-2; KEPCO transmission and distribution facility use rules (31 July 2024) Article 10; Korea Energy Agency solar project procedure guide. Construction day figures are from our scheduling model calibrated on company projects.